<listing id="vjp15"></listing><menuitem id="vjp15"></menuitem><var id="vjp15"></var><cite id="vjp15"></cite>
<var id="vjp15"></var><cite id="vjp15"><video id="vjp15"><menuitem id="vjp15"></menuitem></video></cite>
<cite id="vjp15"></cite>
<var id="vjp15"><strike id="vjp15"><listing id="vjp15"></listing></strike></var>
<var id="vjp15"><strike id="vjp15"><listing id="vjp15"></listing></strike></var>
<menuitem id="vjp15"><strike id="vjp15"></strike></menuitem>
<cite id="vjp15"></cite>
<var id="vjp15"><strike id="vjp15"></strike></var>
<var id="vjp15"></var>
<var id="vjp15"></var>
<var id="vjp15"><video id="vjp15"><thead id="vjp15"></thead></video></var>
<menuitem id="vjp15"></menuitem><cite id="vjp15"><video id="vjp15"></video></cite>
<var id="vjp15"></var><cite id="vjp15"><video id="vjp15"><thead id="vjp15"></thead></video></cite>
<var id="vjp15"></var>
<var id="vjp15"></var>
<menuitem id="vjp15"><span id="vjp15"><thead id="vjp15"></thead></span></menuitem>
<cite id="vjp15"><video id="vjp15"></video></cite>
<menuitem id="vjp15"></menuitem>

深基坑降水井封井施工方法與流程

文檔序號:11127553閱讀:來源:國知局

技術特征:

1.一種深基坑降水井封井施工方法,其特征在于采取以下步驟:

1)機械開挖基坑至原狀地基土,達到集水井底標高(9)位置;

2)夯打埋入混凝土濾水管(5);

3)安裝降水封井主管,將圓環形鋼板底座(14)安放于混凝土濾水管(5)上部并對正,并預先穿入降水井密封圈(4)并對正;

4)依次穿過降水封井主管、混凝土濾水管(5),放入潛水泵(7)附帶潛水泵電纜(6)及抽水膠皮管(8);

5)在降水封井主管頂部安裝蓋板套件,蓋板套件包括抽水蓋板(19)、主抽水管(18)及潛水泵電纜進線管(20),主抽水管(18)和潛水泵電纜進線管(20)均貫穿抽水蓋板(19),將抽水膠皮管(8)上部與主抽水管(18)相連接,并用固定銅絲(3)綁扎牢靠,潛水泵電纜(6)穿出潛水泵電纜進線管(20);

6)在降水井密封圈(4)上部將蓋板套件與降水封井主管用主法蘭緊固螺栓(12)固定;

7)主抽水管(18)頂部設有排水管連接法蘭盤(17),在排水管連接法蘭盤(17)上放置排水管密封圈(16),將排水管結合器(15)通過排水管緊固螺栓連接至排水管連接法蘭盤(17)上,并擰緊;

8)啟動潛水泵(7),進行降水作業,并將地下水降至工作面以下至少500mm;

9)待邊坡土質晾干后,修整邊坡;

10)綁扎筏板鋼筋,安裝混凝土止水鋼板(2),澆筑筏板混凝土(1);

11)保持降水直至筏板基礎全部施工完成,達到停止降水條件;

12)拆除主法蘭緊固螺栓(12),并同步移除潛水泵(7)、抽水膠皮管(8)附帶固定銅絲(3)、潛水泵電纜(6);

13)安裝降水井密封圈(4),同步安裝封井蓋板(11),并緊固;

14)澆筑降水井封閉混凝土(10)。

2.根據權利要求1所述的深基坑降水井封井施工方法,其特征在于:降水封井主管上設置主管止水板(13),主管止水板(13)設置為兩個,軸向分布在降水封井主管上。